Land Acquisition Delays: Reliance Power terminates 3,960 MW Tilaiya power plant

Land Acquisition Delays: Reliance Power terminates 3,960 MW Tilaiya power plant

  • Representational image File Photodna Research & Archives

Anil Ambani-led Reliance Power today said it has terminated the contract for Rs 36,000 crore Tilaiya ultra mega power project in Jharkhand over inordinate delays in land acquisition.

The firm had, in August 2009, won rights to set up a 3,960 MW power plant at Hazaribagh in Jharkhand after bidding a levelised tariff of Rs 1.77 per unit but couldn’t start work on the project as the state government had not provided the required land even after more than five years.

Jharkhand Integrated Power Ltd, a wholly-owned subsidiary of Reliance Power, “has terminated the Power Purchase Agreement (PPA) of its 3,960 MW Tilaiya Ultra Mega Power Project (UMPP) in district Hazaribagh, Jharkhand,” the company said in a statement.

JIPL, a special purpose vehicle created for implementing the project, had signed PPA with 18 power off-takers in 10 states for 25 years. The project was based on captive coal blocks for which coal was to be sourced from Kerendari BC coal mine block.

The total land requirement for the project was over 17,000 acres.

According to the statement, there has been a delay of over 5 years in land acquisition by the state government for the power plant, captive coal blocks and related infrastructure.

The PPA required procurers to handover land and other clearances by February 2010.

“However, the required land is yet to be made available. Even the forest land in the power station area, for which the Stage-II Forest Clearance was accorded by central government way back in November 2010, has not been handed over to JIPL till now.