PM chairs meeting of Chief Ministers of North East States Infrastructure development, key element, says PM


Source: / Press Information Bureau


New Delhi, January 20 2014 : The Prime Minister, Dr Manmohan Singh held a meeting with the Chief Ministers of North East Region to review the progress of infrastructure projects in the region.


The meeting was organised by the Planning Commission which is the nodal agency initiating and monitoring developmental work in North East region.


Opening the meeting, the Prime Minister said that the Government viewed infrastructure development in the North East as a key element in the strategy for developing the region and increasing connectivity with the rest of the country.


Deputy Chairman of the Planning Commission, Dr Montek Singh Ahluwalia made a detailed presentation on Infrastructure Development in the region and noted that continuous focus on the region has led to satisfactory results during the 11th Plan period.


The State Domestic Product growth in the region has been above the national average for the first time ever in the 11th Plan underscoring success of the initiatives and constant monitoring by the Planning Commission.


The GSDP of North East region grew nearly 10% during the 11th Plan period from 2007-2012 compared to 8% for the country as a whole.


This growth was supported by good agriculture sector performance including horticulture, floriculture, fisheries, rubber and oil palm production.


















Prime Minister Dr Manmohan Singh chairing a meeting of NE Chief Ministers
Prime Minister Dr Manmohan Singh chairing a meeting of NE Chief Ministers


It was also noted by Deputy Chairman, Planning Commission that during the same period total Central Assistance including NCA, ACA, SCA and SPA had more than doubled to the region from Rs 34764 crore during the 10th Plan to Rs 73374 crore during the 11th Plan period.


As a result, Plan Expenditure has grown significantly in all NE states as share of GSDP.


In his concluding remarks, the Prime Minister noted that “very considerable progress is being made in each of the sectors reviewed today”.


He directed the Planning Commission to constitute a Monitoring Committee with representatives from the North East states to improve coordination among Central ministries.


Central Ministries have focused on development of infrastructure including Railways, Roads, Airports, Telecom and Power.


Highlights of the review in individual infrastructure sectors .


Railways


The Twelfth Plan initiated a major expansion in railway development in the region.


There are 20 Railway projects under way of which 10 are national projects.


Highlights are: � Additional financial resources of Rs 314 crore were made available in the current year to allow completion of Rangiya-Rangpura (Tezpur), Rangpura- North Lakhimpur and North Lakhimpur- Murkongselek.


o Lumding � Silchar gauge conversion for main and branch lines.


Additional resources of Rs 100 crore were provided in current year.


Expected completion – March 2015 for main line and June 2016 for branch


o Bogibeel Rail cum road bridge across Brahmaputra to be completed by Dec 2016.


o New broadgauge line Dudhnoi – Mendipathar to be completed by March 2014 will be the first rail connectivity to Meghalaya.


o New broad gauge line Harmuti-Naharlagun to be completed by March 2014 will be the first rail connectivity to Arunachal Pradesh.


o The following seven national projects will be completed in the Twelfth Plan: Rangiya-Murkongselek (Assam), Lumding- Silchar including branch lines (Assam, Manipur, Mizoram, Tripura), Tetelia- Byrnihat (Meghalaya), Jiribam-Tupul-Imphal (Manipur), Bogibeel bridge (Assam), Kumarghat-Agartala (Tripura), Agartala-Subroom (Tripura)


Road Development


o The East West Corridor of the National Highways in the North East is 500 km.


81 % is complete and likely completion date is December 2014.Govt of Assam has to resolve some land availability issues.


o The Special Accelerated Road Development Project involves development of 4099 km of roads in phase A.Of this, 2505 km have been sanctioned and 1215 km are complete.


Various steps taken to improve implementation were reviewed.


Targeted completion dates for various stretches are between June 2015 to March 2017.


o The Trans Arunachal Highway programme involves a length of 2319 km of which 58 percent is sanctioned.


Completion date for various stretches is between June 2016 and March 2018.Additional six projects implementation units set up to speed up work.


Actions needed to speed up implementation, including action by State governments in several areas, was reviewed.


Power o The North East currently has 4080 MW of generation capacity and another 6810 MW are under development.


Untapped hydro potential is 55,561 MW and development of this potential would generate surplus power meeting the energy needs of the nation and also generating resources for the region.


o There is need for expeditious environmental and forest clearances and also land acquisition.


Ministry of Environment has recently issued fresh guidelines which will help.


The Cabinet Committee on Investment cleared the Dibang project recently.







via NorthEast Calling - NorthEast India | India's No1 online News Magazine http://ift.tt/KzD47j